Damietta Slaughterhouse – Advanced Wastewater Treatment Plant

Egypt
2024-06-12
400 m³/day
6 Months
Damietta-Slaughterhouse

Overview

RAK Industrial Solutions designed, supplied, installed, and commissioned a state-of-the-art wastewater treatment plant for the Damietta Slaughterhouse, one of Egypt’s largest municipal slaughterhouse facilities. The project was developed to ensure full compliance with the stringent environmental requirements governing wastewater discharge into natural water bodies.

The treatment facility was designed to handle wastewater generated from slaughterhouse operations with an average flow rate of approximately 400 m³/day. Due to the high organic load and the critical environmental sensitivity of the receiving water body, the treatment process was engineered to achieve advanced pollutant removal and stable long-term operation.

The treatment train begins with blood separation and collection systems, followed by coarse and fine screening units, a large equalization tank, chemical treatment and Dissolved Air Flotation (DAF) technology for the removal of fats, oils, grease, and suspended solids.

The biological treatment stage incorporates dedicated High-Load and Low-Load Aeration Tanks equipped with MBBR (Moving Bed Biofilm Reactor) media, significantly increasing the biological surface area while reducing reactor footprint and improving treatment efficiency. Final polishing is achieved through clarification, chlorination, and advanced filtration systems to ensure compliance with discharge regulations.

The facility also includes a high-capacity Screw Press Sludge Dewatering System and a fully equipped laboratory for continuous monitoring and analysis of wastewater quality, plant performance, and regulatory compliance.

The project was developed to meet the requirements of Egyptian Environmental Law No. 48 of 1982 governing wastewater discharge into surface water bodies. The treated effluent is discharged in accordance with strict environmental standards, supporting the protection of sensitive aquatic ecosystems and national water resources.

Damietta-Slaughterhouse
Damietta-Slaughterhouse
Damietta-Slaughterhouse
Damietta-Slaughterhouse
Damietta-Slaughterhouse
Damietta-Slaughterhouse
Damietta-Slaughterhouse
Damietta-Slaughterhouse
Damietta-Slaughterhouse
Damietta-Slaughterhouse
Damietta-Slaughterhouse
Damietta-Slaughterhouse
Damietta-Slaughterhouse
Damietta-Slaughterhouse
Damietta-Slaughterhouse
Damietta-Slaughterhouse
Damietta-Slaughterhouse
Damietta-Slaughterhouse
Damietta-Slaughterhouse
Damietta-Slaughterhouse
Damietta-Slaughterhouse
Damietta-Slaughterhouse
Damietta-Slaughterhouse
Damietta-Slaughterhouse
Damietta-Slaughterhouse
Damietta-Slaughterhouse
Damietta-Slaughterhouse
Damietta-Slaughterhouse
Damietta-Slaughterhouse

Project Information

Location

Egypt

Project Date

2024-06-12

Capacity

400 m³/day

Execution Period

6 Months

Key Features

  • Capacity: 400 m³/day

  • Municipal Slaughterhouse Application

  • Blood Separation System

  • Coarse & Fine Screening

  • Large Equalization Tank

  • Chemical Treatment Process

  • DAF Technology

  • High-Load & Low-Load Biological Treatment

  • MBBR Technology

  • Chlorination System

  • Advanced Filtration Units

  • Screw Press Sludge Dewatering

  • Fully Equipped Laboratory

  • Compliance with Egyptian Environmental Regulations

  • Protection of Surface Water Resources